Multiple Choice
Consider a work center with a demand rate of 20 parts per hour and using a container that can hold 5 parts. It is estimated that the container takes 30 minutes to cycle through the work cell. Assume a safety stock level of 10 percent. What is the value of C for this system?
A) 5
B) 0.5
C) 0.1
D) 20
Correct Answer:

Verified
Correct Answer:
Verified