Multiple Choice
If WIP levels are reasonable and product flow is steady, then the input rate for a job shop should be?
A) Equal to the daily output rate
B) Less than the daily output rate
C) More than the daily output rate
D) WIP and input rate are unrelated
Correct Answer:

Verified
Correct Answer:
Verified