Multiple Choice
Two jobs (J1 and J2) are scheduled on two workcenters (WCA and WCB) . J1 starts at time 0 on WCA and finishes on that workcenter at time 5. J2 starts at time 0 on WCB and finishes at time 3. J2 then starts on WCA at time 5 and finishes at time 9. What is the makespan of these jobs?
A) 0
B) 5
C) 9
D) Cannot be determined from the information given
Correct Answer:

Verified
Correct Answer:
Verified