Multiple Choice
You know when you have arrived at the optimal solution in using the time-cost CPM scheduling model analysis when what happens?
A) You have found the critical path.
B) You have run out of crash time.
C) You no longer have a linear relationship with costs.
D) You have reached the minimum total cost.
E) You have run out of crash costs.
Correct Answer: