Multiple Choice
Some of the advantages of a functional project where the project is housed in a functional division include which of the following?
A) The project manager has full authority over the project.
B) Team pride, motivation, and commitment are high.
C) A team member can work on several projects.
D) Needs of the client are secondary.
E) None of these choices are correct
Correct Answer:

Verified
Correct Answer:
Verified