Multiple Choice
Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by one day, what is the total time of the project and total cost?
A) Total time is 13 days, total cost is $1,500.
B) Total time is 12 days, total cost is $2,000.
C) Total time is 12 days, total cost is $2,300.
D) Total time is 11 days, total cost is $1,850.
E) Total time is 11 days, total cost is $2,350.
Correct Answer:

Verified
Correct Answer:
Verified
Q76: A project milestone is a specific event
Q77: Which of the following is not an
Q78: A project can be subdivided into which
Q79: Slack activity time is the difference between
Q80: A project has four activities: A, B,
Q82: Complex projects are often subdivided into a
Q83: Derivative projects are those that address incremental
Q84: A project has four activities: A, B,
Q85: Earned value management (EVM) is a technique
Q86: The activity direct costs associated with a