Multiple Choice
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the schedule variance for the project?
A) Under 1.00K
B) 1.00K− 1.20K
C) 1.21K− 1.40K
D) 1.41K − 1.60K
E) Over 1.60K
Correct Answer:

Verified
Correct Answer:
Verified
Q79: Slack activity time is the difference between
Q80: A project has four activities: A, B,
Q81: Here are the data for a time-cost
Q82: Complex projects are often subdivided into a
Q83: Derivative projects are those that address incremental
Q85: Earned value management (EVM) is a technique
Q86: The activity direct costs associated with a
Q87: Pieces of work within a project that
Q88: A project has four activities: A, B,
Q89: In a CPM analysis, if you subtract