Multiple Choice
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for the project?
A) $0 − $15K
B) $15.01K − $30K
C) $40.01K − $45K
D) $45.01K − $60K
E) Over $60K
Correct Answer:

Verified
Correct Answer:
Verified
Q75: A specific event in a project is:<br>A)
Q76: A project milestone is a specific event
Q77: Which of the following is not an
Q78: A project can be subdivided into which
Q79: Slack activity time is the difference between
Q81: Here are the data for a time-cost
Q82: Complex projects are often subdivided into a
Q83: Derivative projects are those that address incremental
Q84: A project has four activities: A, B,
Q85: Earned value management (EVM) is a technique