Multiple Choice
You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,What is the total (i.e., direct and indirect) project cost?
A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500
Correct Answer:

Verified
Correct Answer:
Verified
Q57: One of the assumptions made using CPM
Q58: A simple project listing of five activities,
Q59: A work breakdown structure is used in
Q60: Which of the following is not an
Q61: In this structure, each project uses people
Q63: One of the advantages of a functional
Q64: You are looking at a chart that
Q65: In this structure, team members are assigned
Q66: A project has four activities: A, B,
Q67: Functional projects have high levels of team