Multiple Choice
In this structure, team members are assigned from the functional units of the organization. The team members remain a part of their functional units and typically are not dedicated to the project.
A) Pure project
B) Modified project
C) Functional project
D) Hybrid project
E) Matrix project
Correct Answer:

Verified
Correct Answer:
Verified