Multiple Choice
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the cost performance index for the project?
A) Less than zero
B) 0 − 1.05
C) 1.051 − 1.10
D) 1.11 − 1.15
E) Over 1.15
Correct Answer:

Verified
Correct Answer:
Verified
Q61: In this structure, each project uses people
Q62: You have collected the data for a
Q63: One of the advantages of a functional
Q64: You are looking at a chart that
Q65: In this structure, team members are assigned
Q67: Functional projects have high levels of team
Q68: A structure for organizing a project where
Q69: In CPM analysis, it is generally expected
Q70: For an activity in a CPM analysis,
Q71: What is a work breakdown structure?<br>A) A