Multiple Choice
You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.
At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ?
A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days
Correct Answer:

Verified
Correct Answer:
Verified
Q29: The Gantt chart is an example of
Q30: You have just used the network planning
Q31: A company must perform a maintenance project
Q32: You have the following time and cost
Q33: CPM is an abbreviation for critical path
Q35: You know when you have arrived at
Q36: A matrix project attempts to blend properties
Q37: Some of the advantages of a functional
Q38: An activity has an optimistic time of
Q39: Calculating the early start and early finish