A Project Has Four Activities: A, B, C, and D

Question 94

Multiple Choice

A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the cost variance for the project?


A) Under 1.00K
B) 1.00K− 1.20K
C) 1.21K− 1.40K
D) 1.41K − 1.60K
E) Over 1.60K