Question 92

Multiple Choice

Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. <sub> </sub>   What are the total time of this project and total normal cost? A)  Total time is 13 days, total cost is $1,200. B)  Total time is 12 days, total cost is $1,700. C)  Total time is 11 days, total cost is $1,600. D)  Total time is 10 days, total cost is $1,750. E)  Total time is 9 days, total cost is $1,700. What are the total time of this project and total normal cost?


A) Total time is 13 days, total cost is $1,200.
B) Total time is 12 days, total cost is $1,700.
C) Total time is 11 days, total cost is $1,600.
D) Total time is 10 days, total cost is $1,750.
E) Total time is 9 days, total cost is $1,700.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions