Multiple Choice
You have just been assigned to oversee a series of projects. Functional areas will loan you personnel for each project, and separate project managers will be responsible for separate projects. These project managers will report to you. Which project management structure is being used?
A) Pure project
B) Task force
C) Matrix project
D) Functional project
E) PERT
Correct Answer:

Verified
Correct Answer:
Verified