Multiple Choice
Table J.8
Auto Data produces custom engineering testing equipment. The following six jobs are currently in the design department. The time since each one arrived, the processing time, and the due date are shown below. All times are expressed in terms of days. Let now be the beginning of Day 1.
-Using the information in Table J.8 and the FCFS rule, what is the average days past due?
A) fewer than or equal to 5.0 days
B) greater than 5.0 days but fewer than or equal to 8.0 days
C) greater than 8.0 days but fewer than or equal to 9.0 days
D) greater than 9.0 days
Correct Answer:

Verified
Correct Answer:
Verified
Q87: An appropriate objective for a manufacturing firm
Q88: Critical ratio (CR) is a single-dimension priority
Q89: A rule that establishes a job's priority
Q90: The percent of work time productively spent
Q91: The earliest due date (EDD) rule gives
Q93: Table J.18<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table J.18
Q94: Table J.6<br>All of the following three jobs
Q95: Table J.17<br>A company must take on seven
Q96: A first-come, first-served schedule minimizes the average
Q97: Table J.11<br>Work center Q45 has four jobs