Multiple Choice
Table J.17
A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
-Using the information in Table J.17 and Johnson's rule, develop a schedule that minimizes makespan for these seven jobs. Assume that job C could be neatly split into two equal parts, each having half of the processing time on each machine as the full job C. Using your original sequence, but splitting job C, what is the makespan for the seven jobs?
A) between 58 and 59 days
B) between 56 and 57 days
C) between 55 and 56 days
D) between 57 and 58 days
Correct Answer:

Verified
Correct Answer:
Verified
Q90: The percent of work time productively spent
Q91: The earliest due date (EDD) rule gives
Q92: Table J.8<br>Auto Data produces custom engineering testing
Q93: Table J.18<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table J.18
Q94: Table J.6<br>All of the following three jobs
Q96: A first-come, first-served schedule minimizes the average
Q97: Table J.11<br>Work center Q45 has four jobs
Q98: Table J.8<br>Auto Data produces custom engineering testing
Q99: When using the critical ratio (CR) priority
Q100: Consider this list of jobs that have