Multiple Choice
Table J.6
All of the following three jobs just arrived (end of hour 0) at Workstation A. They are the only ones waiting to be processed.
-Use the information in Table J.6. What is the job sequence at Workstation A, using the critical ratio rule?
A) 3-2-1
B) 1-2-3
C) 1-3-2
D) 2-1-3
Correct Answer:

Verified
Correct Answer:
Verified
Q89: A rule that establishes a job's priority
Q90: The percent of work time productively spent
Q91: The earliest due date (EDD) rule gives