Table J.9
There are three jobs available for processing at Workstation 1. They just arrived at Workstation 1, at the end of Day 0.
-Using the information in Table J.9 and the slack per remaining operation (S/RO) rule, what is the average days past due?
A) fewer than or equal to 6.0 days
B) greater than 6.0 days but fewer than or equal to 8.0 days
C) greater than 8.0 days but fewer than or equal to 9.0 days
D) greater than 9.0 days