Use the Information in the Table and Sequence the Six

Question 75

Essay

Use the information in the table and sequence the six jobs using SPT and EDD. Calculate the average flow times and average lateness. All jobs arrived at time zero and are ready at time zero.
Use the information in the table and sequence the six jobs using SPT and EDD. Calculate the average flow times and average lateness. All jobs arrived at time zero and are ready at time zero.

Correct Answer:

verifed

Verified

blured image
Average Flow Time = 51.67
Av...