Consider the Following Problems in Which Four Jobs Must Each

Question 77

Essay

Consider the following problems in which four jobs must each be processed on two machines starting with Machine A and then going to Machine B. The following processing times are available (in hours):
Consider the following problems in which four jobs must each be processed on two machines starting with Machine A and then going to Machine B. The following processing times are available (in hours):     What is the minimum makespan for this group of jobs? Depict it graphically using a Gantt chart.
What is the minimum makespan for this group of jobs? Depict it graphically using a Gantt chart.

Correct Answer:

verifed

Verified

The optimal sequence...