Multiple Choice
A standard work year is 2,000 hours at the Luther Mill and it takes about an hour and a half to fill a customer order. Last year saw 25,000 customer orders at the mill and the manager has a rebuilt Ford 9N in mind as a company car, so he hopes that there is an increase of 2% in customer orders for next year. If the manager hires twenty workers, what is the capacity cushion?
A) 3.8%
B) 3.1%
C) 5.1%
D) 4.3%
Correct Answer:

Verified
Correct Answer:
Verified