Essay
The Union Manufacturing Company is producing two types of products: A and B. The demand forecasts, batch size, and time standards for the Mark I operation follow:
The company works 250 days per year and operates 2 shifts, each covering 8 hours. If a 20 percent capacity cushion is maintained, how many new Mark I machines are required if Union does not resort to any short-term capacity options?