Multiple Choice
The second step in Theory of Constraints application, "exploit the bottleneck(s) ," means that the analyst should:
A) create a schedule that maximizes the throughput of the bottlenecks.
B) repeat the analysis process to look for other bottlenecks.
C) consider increasing capacity of the bottleneck.
D) schedule non-bottleneck resources to support the bottleneck.
Correct Answer:

Verified
Correct Answer:
Verified
Q28: Which of the following statements concerning line
Q29: To generate the maximum output, the cycle
Q30: Figure 5.3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.3
Q31: Regardless of the number of tasks or
Q32: Table 5.2<br>A company makes four products that
Q34: Table 5.4<br>The Superior Management Company assembles muffalettas
Q35: A bottleneck process has the lowest capacity
Q36: A firm's actual throughput and profit depend
Q37: Table 5.1<br>A company makes four products that
Q38: Figure 5.3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.3