Multiple Choice
Figure 5.3
The figure above shows the process for customers arriving at Hobbies Unlimited for several advertised crafts demonstrations. After signing in, customers are routed to different locations in the store for the two different programs provided. The numbers in parentheses are the time in minutes for each step of the process.
-Use the information in Figure 5.3. How many customers can be processed through the A-B-E-F-G routing during a 4-hour evening session?
A) 8
B) 24
C) 12
D) 32
Correct Answer:

Verified
Correct Answer:
Verified
Q33: The second step in Theory of Constraints
Q34: Table 5.4<br>The Superior Management Company assembles muffalettas
Q35: A bottleneck process has the lowest capacity
Q36: A firm's actual throughput and profit depend
Q37: Table 5.1<br>A company makes four products that
Q39: Figure 5.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.2
Q40: A(n) _ line is a product line
Q41: Figure 5.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.2
Q42: Short term capacity planning should be driven
Q43: Table 5.4<br>The Superior Management Company assembles muffalettas