Table 5.3
King Supply makes four different types of plumbing fixtures: W, X, Y and Z. The contribution margins for these products are: $70 for Product W, $60 for Product X, $90 for Product Y and $100 for Product Z. Fixed overhead is estimated at $5,500 per week. The manufacture of each fixture requires four machines, Machines #1, 2, 3 and 4. Each of the machines is available for 40 hours a week and there is no setup time required when shifting from the production of one product to any other. The processing requirements to make one unit of each product are shown in the table. Weekly product demand for the next planning period has been forecasted as follows: 70 Ws, 60 Xs, 50 Ys and 30 Zs.
In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 5.3. Using the bottleneck method, in what sequence should products be scheduled for production?
A) Z, Y, X, W
B) X, W, Z, Y
C) Z, Y, W, X
D) X, Y, Z, W
Correct Answer:

Verified
Correct Answer:
Verified
Q88: Line balancing strives to create workstations so
Q89: Table 5.3<br>King Supply makes four different types
Q90: Figure 5.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.1
Q91: Consider the following production process. It is
Q92: A line balance that is 100% efficient
Q94: Figure 5.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.4
Q95: The traditional method of determining contribution margin
Q96: Table 5.1<br>A company makes four products that
Q97: Table 5.6<br>Balance the following line for an
Q98: Work should be released into the system