Solved

Consider the Following Production Process

Question 91

Essay

Consider the following production process. It is trying to meet a market demand of 500 units per week.
Consider the following production process. It is trying to meet a market demand of 500 units per week.     Step 1: Material release schedule Step 2: Drilling (capacity is 500 units/week) Step 3: Tapping (capacity is 450 units/week) Step 4: Grinding (capacity is 600 units/week) Step 5: Coating (capacity is 400 units/week) Step 6: Inspection (capacity is 1,000 units/week) a. Where should buffers be placed? b. Which resource is the drum? c. Where should the rope be placed? d. Which resource is the bottleneck? e. Which resource is the CCR?
Step 1: Material release schedule
Step 2: Drilling (capacity is 500 units/week)
Step 3: Tapping (capacity is 450 units/week)
Step 4: Grinding (capacity is 600 units/week)
Step 5: Coating (capacity is 400 units/week)
Step 6: Inspection (capacity is 1,000 units/week)
a. Where should buffers be placed?
b. Which resource is the drum?
c. Where should the rope be placed?
d. Which resource is the bottleneck?
e. Which resource is the CCR?

Correct Answer:

verifed

Verified

a. A constraint buffer should be placed ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions