Essay
Consider the following production process. It is trying to meet a market demand of 500 units per week.
Step 1: Material release schedule
Step 2: Drilling (capacity is 500 units/week)
Step 3: Tapping (capacity is 450 units/week)
Step 4: Grinding (capacity is 600 units/week)
Step 5: Coating (capacity is 400 units/week)
Step 6: Inspection (capacity is 1,000 units/week)
a. Where should buffers be placed?
b. Which resource is the drum?
c. Where should the rope be placed?
d. Which resource is the bottleneck?
e. Which resource is the CCR?
Correct Answer:

Verified
a. A constraint buffer should be placed ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q86: Balance the assembly line for the tasks
Q87: The Theory of Constraints method is also
Q88: Line balancing strives to create workstations so
Q89: Table 5.3<br>King Supply makes four different types
Q90: Figure 5.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.1
Q92: A line balance that is 100% efficient
Q93: Table 5.3<br>King Supply makes four different types
Q94: Figure 5.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 5.4
Q95: The traditional method of determining contribution margin
Q96: Table 5.1<br>A company makes four products that