Multiple Choice
In a network diagram, an activity:
A) is the largest unit of work effort consuming both time and resources that a project manager can schedule and control.
B) is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.
C) should always be something the company has had experience with.
D) must always have a single, precise estimate for the time duration.
Correct Answer:

Verified
Correct Answer:
Verified
Q39: Figure 7.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 7.2
Q40: Table 7.9<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.9
Q41: Figure to accompany Table 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q42: Table 7.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.4
Q43: You are given the following information about
Q45: The project's objective statement should contain:<br>A) slack
Q46: The project manager and team can step
Q47: _ determines the sequence for undertaking activities.
Q48: Table 7.14<br>You are responsible for managing a
Q49: The network diagram is a planning method