Multiple Choice
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 7.14, what is the probability of completing the project in 29 or fewer weeks?
A) less than or equal to 40%
B) greater than 40% but less than or equal to 45%
C) greater than 45% but less than or equal to 50%
D) greater than 50%
Correct Answer:

Verified
Correct Answer:
Verified
Q43: You are given the following information about
Q44: In a network diagram, an activity:<br>A) is
Q45: The project's objective statement should contain:<br>A) slack
Q46: The project manager and team can step
Q47: _ determines the sequence for undertaking activities.
Q49: The network diagram is a planning method
Q50: Figure to accompany Table 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q51: The normal cost is the amount of
Q52: The _ is the shortest possible time
Q53: Figure to accompany Table 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"