Multiple Choice
Table 7.9
-Using Table 7.9, what is the earliest completion time of this project if normal times are used for all activities?
A) fewer than 13 weeks
B) 13 weeks
C) 14 weeks
D) more than 14 weeks
Correct Answer:

Verified
Correct Answer:
Verified