Multiple Choice
A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=6.
A) The critical path is D-E-F, duration 12.
B) The critical path is D-F, duration 10.
C) Slack at D is 0 periods.
D) Slack at E is 3 periods.
E) Both A and C are true.
Correct Answer:

Verified
Correct Answer:
Verified