Multiple Choice
A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or more?
A) -0.40000
B) 0.02275
C) 0.34444
D) 0.97725
E) 4.20000
Correct Answer:

Verified
Correct Answer:
Verified
Q120: How is the expected completion time of
Q121: If an activity whose normal duration is
Q122: The control of projects involves close monitoring
Q123: A simple CPM network has three activities,
Q124: The _ is the computed longest time
Q126: The project organization works best when which
Q127: Agile project management is a type of
Q128: Analysis of a PERT problem shows the
Q129: _ is decreasing activity time in a
Q130: The critical path for the network activities