A Local Project Being Analyzed by PERT Has 42 Activities

Question 125

Multiple Choice

A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or more?


A) -0.40000
B) 0.02275
C) 0.34444
D) 0.97725
E) 4.20000

Correct Answer:

verifed

Verified