Multiple Choice
The project organization works best when which of the following conditions are satisfied? I. Work tasks can be defined with a specific goal and deadline.
II. The job is typical and familiar to the existing organization.
III. The work contains interrelated tasks requiring specialized skills.
IV. The project is temporary but unimportant to long-term organizational success.
V. The project cuts across organizational lines.
A) I, II, III, IV, V
B) None of these conditions need to be satisfied.
C) I, III, V
D) I, II, III, V
E) I, III, IV, V
Correct Answer:

Verified
Correct Answer:
Verified
Q121: If an activity whose normal duration is
Q122: The control of projects involves close monitoring
Q123: A simple CPM network has three activities,
Q124: The _ is the computed longest time
Q125: A local project being analyzed by PERT
Q127: Agile project management is a type of
Q128: Analysis of a PERT problem shows the
Q129: _ is decreasing activity time in a
Q130: The critical path for the network activities
Q131: Project managers often use the waterfall approach