The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6.
(a) What task must be on the critical path, regardless of activity durations?
(b) What is the duration of path A-B-E-H-J?
(c) What is the critical path of this network?
(d) What is the length of the critical path?
(e) What is slack time at activity H?
(f) What is the Late Finish of activity H?
(g) If activity C was delayed by six time units, what would happen to the project duration?
Correct Answer:

Verified
(a) J; (b) 20; (c) A-B-G-I-J; ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q85: Contract requirements state that a project must
Q86: The ES of an activity that has
Q87: What are the earliest activity start time
Q88: Which of the following statements regarding Bechtel
Q89: The fundamental difference between PERT and CPM
Q91: A network consists of the activities in
Q92: Identify the responsibilities of project managers.
Q93: The critical path for the network activities
Q94: A network has been crashed to the
Q95: The bell curve is often appropriate for