Solved

The Network Below Represents a Project Being Analyzed by the Critical

Question 90

Essay

The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6.
The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6.    (a) What task must be on the critical path, regardless of activity durations? (b) What is the duration of path A-B-E-H-J? (c) What is the critical path of this network? (d) What is the length of the critical path? (e) What is slack time at activity H? (f) What is the Late Finish of activity H? (g) If activity C was delayed by six time units, what would happen to the project duration? (a) What task must be on the critical path, regardless of activity durations?
(b) What is the duration of path A-B-E-H-J?
(c) What is the critical path of this network?
(d) What is the length of the critical path?
(e) What is slack time at activity H?
(f) What is the Late Finish of activity H?
(g) If activity C was delayed by six time units, what would happen to the project duration?

Correct Answer:

verifed

Verified

(a) J; (b) 20; (c) A-B-G-I-J; ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions