menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Operations Management Sustainability Study Set 4
  4. Exam
    Exam 3: Project Management
  5. Question
    The ES of an Activity That Has Only One Predecessor
Solved

The ES of an Activity That Has Only One Predecessor

Question 86

Question 86

True/False

The ES of an activity that has only one predecessor is simply the EF of that predecessor.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q81: The waterfall approach is used most often

Q82: Identify each of the purposes of project

Q83: A project whose critical path has an

Q84: Two activities on different critical paths that

Q85: Contract requirements state that a project must

Q87: What are the earliest activity start time

Q88: Which of the following statements regarding Bechtel

Q89: The fundamental difference between PERT and CPM

Q90: The network below represents a project being

Q91: A network consists of the activities in

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines