Multiple Choice
Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?
A) 0.04006
B) 0.45994
C) 0.80511
D) 0.95994
E) near 1.00000, or almost certain
Correct Answer:

Verified
Correct Answer:
Verified
Q80: A code of ethics especially for project
Q81: The waterfall approach is used most often
Q82: Identify each of the purposes of project
Q83: A project whose critical path has an
Q84: Two activities on different critical paths that
Q86: The ES of an activity that has
Q87: What are the earliest activity start time
Q88: Which of the following statements regarding Bechtel
Q89: The fundamental difference between PERT and CPM
Q90: The network below represents a project being