Multiple Choice
Who is responsible for the detailed project plan?
A) the project's sponsor
B) the government
C) the Canadian Engineering Association
D) the project's manager
E) the financial institution who finances the project
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q40: Identify some similarities and differences between the
Q41: Which of the following project management tools
Q42: At what stage of a project's lifecycle
Q43: The AON diagram shown represents a project.
Q44: As a rule, each project includes a
Q45: The AON diagram shown represents a project.
Q46: A construction company has just started building
Q47: Developing a new electronics product involves two
Q48: What is "crashing"?<br>A)time until a capital asset
Q50: A 5-year project requires $10 million in