Multiple Choice
When resources such as overtime, extra equipment, and additional staff result in higher costs, what should a project manager do?
A) Hire additional staff and acquire additional resources.
B) Terminate the project.
C) Make a tradeoff between the extra costs associated with crashing and the benefits of a reduced project completion time.
D) Look for a new sponsor of the project.
E) Delay the project until economic conditions change.
Correct Answer:

Verified
Correct Answer:
Verified