Multiple Choice
In order to calculate the crash cost per unit of time, a project manager has to know
A) the project's costs, benefits and service life.
B) the project's normal and crash costs as well as normal and crash time.
C) the project's equivalent annual costs and crash time.
D) the project's economic life and its crash costs.
E) the project's crash and normal time as well as the project's costs and benefits.
Correct Answer:

Verified
Correct Answer:
Verified