    The Simplest Way to Reduce Cost on a Project Is
Solved

The Simplest Way to Reduce Cost on a Project Is

Question 93

Question 93

Multiple Choice

The simplest way to reduce cost on a project is to reduce the scope of a project.


A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q88: Crashing a more expensive activity may be

Q89: There are fewer options available for reducing

Q90: Why is the project duration with the

Q91: The relationship between the normal point and

Q92: If indirect costs are a significant percentage

Q94: When reducing project duration, the crash cost

Q95: One of the advantages of using a

Q96: When do you know you have crashed

Q97: Costs such as labor, materials, equipment, or

Q98: Reducing project duration<br>A) involves crashing all activities

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines