Multiple Choice
When the project team is salaried, which of the following is the preferred choice for accelerating project completion?
A) Assign additional staff and equipment
B) Subcontract work
C) Schedule overtime
D) Outsource project work
E) Establish a core project team
Correct Answer:

Verified