Multiple Choice
A project leader's boss has indicated that their project is very important. If the critical path is delayed, the lead will be given whatever is needed to get it back on schedule. The project is classified as ________ constrained.
A) time
B) quality
C) cost
D) performance
E) resource
Correct Answer: