Multiple Choice
Splitting an activity can result in all of the following EXCEPT
A) more people working on the same activity.
B) possible startup and shutdown costs.
C) a resource being moved from one activity to another and then back.
D) activity work being placed on hold for a period until more resources are available.
E) a better project schedule.
Correct Answer:

Verified
Correct Answer:
Verified