Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node. The project is time-constrained and the project manager wishes to minimize the number of resources required at any given time. Each activity requires a single resource.
A) Activity B
B) Activity C
C) Activity D
D) Both activities C and D
E) Either activity B or activity D
Correct Answer:

Verified
Correct Answer:
Verified
Q20: In a resource-constrained project the second priority
Q21: Comparing Planned Costs versus Actual Costs will
Q22: A project leader's boss has indicated that
Q23: Why is it critical to form a
Q24: Sequential activities hold just as much potential
Q26: Splitting an activity can result in all
Q27: Since resource leveling or smoothing delays noncritical
Q28: Project budgets are developed by time-phasing which
Q29: Why should project managers be cautious about
Q30: What is the difference in project goals