Multiple Choice
A project budget report is showing our project as spending $50,000 against a budgeted amount of $65,000. Which of the following is true?
A) We are spending less than we should for the project.
B) We are doing a good job managing the project.
C) We should check to see if all the bills have been paid.
D) We have more money to put into budget reserves.
E) We can't be sure how the project is going.
Correct Answer:

Verified
Correct Answer:
Verified