Question 89

Multiple Choice

Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday) . Assume no working-day holidays during the months of May and June-no Memorial Day holiday, for example.


A) Monday, May 18, 2020
B) Tuesday, May 19, 2020
C) Wednesday, May 20, 2020
D) Sunday, May 17, 2020
E) Saturday, May 16, 2020