Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday) . Assume no working-day holidays during the months of May and June-no Memorial Day holiday, for example.
A) Monday, May 18, 2020
B) Tuesday, May 19, 2020
C) Wednesday, May 20, 2020
D) Sunday, May 17, 2020
E) Saturday, May 16, 2020
Correct Answer:

Verified
Correct Answer:
Verified