Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume all activities require the same resource.
A) Activity B
B) Activity C
C) Activity D
D) Both activities B and D
E) Either activity B or activity D
Correct Answer:

Verified
Correct Answer:
Verified