Multiple Choice
The critical path in a project network is the
A) shortest path through the network.
B) longest path through the network.
C) network path with the most difficult activities.
D) network path using the most resources.
E) network path with the most merge activities.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q54: It is possible for a project network
Q55: Briefly describe looping and conditional statements and
Q56: In the network computation process what is
Q57: The _ calculates the critical path and
Q58: Different activities along the same path can
Q60: One piece of information that the arrows
Q61: The _ lag is the most typical
Q62: Consider the following table of activities A
Q63: Consider the following table of activities A
Q64: Even though a project network costs time