Multiple Choice
One piece of information that the arrows within the Activity-on-Node network can convey is
A) the duration of an activity.
B) the amount of risk inherent in an activity.
C) how activities are related.
D) ES and EF for the activity.
E) LS and LF for the activity.
Correct Answer:

Verified
Correct Answer:
Verified