Multiple Choice
The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.
A) backward pass
B) universal pass
C) forward pass
D) concurrent pass
E) parallel pass
Correct Answer:

Verified
Correct Answer:
Verified